FEOC compliance for commercial solar in 2026

The Prohibited Foreign Entity rules under OBBBA are now live for commercial solar. What the MACR test requires, what documentation you should demand from your developer before signing, and the recapture risk that runs into the mid 2030s.

By Solara Pro Team|August 4, 2026|10 min read

On July 4, 2025, President Trump signed the One Big Beautiful Bill Act into law. Most commercial solar owners focused on the construction deadline that date created. Fewer noticed the second thing the law did: it added a set of rules that can strip tax credits from a project that clears every other hurdle. A project beginning construction in 2026 must now prove that at least 40 percent of its equipment costs came from non-Chinese sources just to qualify for the base ITC. Get that calculation wrong, or fail to document it, and the entire 30 percent credit disappears. Not reduced. Eliminated.

This is the Foreign Entity of Concern framework, and for commercial solar starting today, it is the most consequential compliance requirement in the current tax code.

What FEOC actually is: the PFE framework under OBBBA

The IRA introduced a narrow version of FEOC rules in 2022, limited to the Section 30D clean vehicle credit. The OBBBA expanded those rules to cover the primary commercial solar credits: Section 48E (Clean Electricity Investment Tax Credit), Section 45Y (Clean Electricity Production Tax Credit), and Section 45X (Advanced Manufacturing Production Credit). Legacy credits under the old Sections 45 and 48 are fully unaffected. Any commercial project beginning construction in 2026 or later operates under the new regime.

The OBBBA introduces a new umbrella term: Prohibited Foreign Entity (PFE). A PFE can be one of two types.

Specified Foreign Entities (SFEs) cover the most direct cases. An SFE is any entity 50 percent or more owned by a government, agency, or citizen of China, Russia, Iran, or North Korea (the Covered Nations). It also covers entities explicitly named in the National Defense Authorization Act for Fiscal Year 2024. In the battery sector, that list names CATL, BYD, Gotion, EVE Energy, Hithium Energy Storage Technology, and Envision Energy (parent of AESC) by statute. Any entity subject to Uyghur Forced Labor Prevention Act restrictions is also an SFE.

Foreign-Influenced Entities (FIEs) are where the complexity compounds. A company becomes a FIE if an SFE can appoint any senior officer or board member; if an SFE holds 25 percent or more equity or voting rights; if multiple SFEs together hold 40 percent or more; if 15 percent or more of its original-issuance debt came from Chinese lenders; or if a contract or licensing agreement gives an SFE what the statute calls "effective control" over the project or its component production. Treasury has not yet published final guidance defining effective control. That open definition is the most significant unresolved risk in the current framework.

The OBBBA creates four independent disqualification mechanisms. A project can fail on any one:

  1. Taxpayer-level prohibition: The entity claiming the credit is itself a PFE. Effective for taxable years beginning after July 4, 2025; for calendar-year taxpayers, that is January 1, 2026.
  2. Material assistance (MACR test): PFE-sourced equipment exceeds the allowed cost threshold. Applies to qualified facilities beginning construction after December 31, 2025.
  3. Licensing with an SFE: A post-July 4, 2025 licensing agreement that covers the project with an SFE automatically makes the taxpayer a FIE, regardless of the supply chain.
  4. Payments conferring effective control: Payments to an SFE under a contract giving the SFE operational authority over the project or its components. This risk runs for 10 years post-commissioning under the recapture provision.

For commercial property owners, this means reviewing not just the equipment supply chain but the capital structure and any ongoing service contracts with Chinese-linked manufacturers.

The MACR thresholds: what 40 percent actually requires

IRS Notice 2026-15, issued February 12, 2026, established the interim framework for calculating the Material Assistance Cost Ratio. The math is straightforward; the data gathering is not.

MACR = (Total direct equipment costs - PFE-sourced costs) / Total direct equipment costs

The ratio must equal or exceed the threshold for the year construction begins. The thresholds ratchet upward through 2030:

Construction YearSolar / Wind Projects (QF)Battery Storage (EST)
202640%55%
202745%60%
202850%65%
202955%70%
2030 and later60%75%

Notice 2026-15 provides three calculation pathways. The direct cost method traces actual costs to each supplier. An identification safe harbor lets developers use the assigned cost percentage tables from existing domestic content notices (primarily Notice 2025-08 for solar PV) to determine which components count and at what weights. A certification safe harbor allows reliance on written supplier attestations that the supplier is not a PFE, provided no contrary knowledge exists.

Steel and iron construction materials are excluded. Polysilicon is excluded. The calculation focuses on manufactured products and components: modules, cells, inverters, battery cells, battery management systems, and structural racking (excluding steel). For a solar-plus-storage project, the MACR must be run separately for the PV array and the battery system using the applicable threshold for each. One combined calculation does not satisfy the requirement.

Treasury is required by statute to publish formal safe harbor cost tables by December 31, 2026. Until those tables arrive, the interim safe harbors in Notice 2026-15 are the operational framework for every project beginning construction in 2026.

The supply chain reality: which equipment is compliant

The 2026 solar module market looks different depending on whether FEOC compliance is required.

FEOC-compliant module manufacturers with U.S. or verified non-FEOC manufacturing include First Solar (thin-film CdTe, manufactured in Ohio and Malaysia), Qcells (wafer-to-module operations in Dalton, Georgia, with Korean cell supply), Silfab Solar (U.S. and Canadian facilities), Heliene Solar (Minnesota), and REC Solar (Norwegian-owned, Malaysian manufacturing). Enphase microinverters carry non-FEOC certifications.

The supply constraint is cells. U.S. domestic cell production capacity stands at roughly 3 to 5 GW against module capacity exceeding 60 GW. T1 Energy's 2.1 GW cell factory in Rockdale, Texas, is scheduled to come online by end of 2026. Qcells' Cartersville upstream facility is targeting full operations by end of 2026. A mid-2026 AD/CVD investigation covering cells from Indonesia, India, and Laos has further narrowed the available FEOC-compliant cell pool.

The price premium for FEOC-compliant modules reflects that constraint. Median U.S. solar module pricing reached approximately $0.28 per watt in Q1 2026, up from $0.25 per watt in early 2025. The differential between FEOC-compliant and FEOC-uncertain supply has been running at roughly $0.03 to $0.05 per watt. On a 500 kW commercial project (roughly 1,250 modules), that is $15,000 to $25,000 in additional equipment cost, well below the $375,000 ITC at stake.

Battery storage faces a harder challenge. According to DOE supply chain data, 90 to 100 percent of U.S. BESS systems contain at least one Chinese-sourced component, and 65 percent of global Tier 1 BESS vendors are headquartered in China. The six manufacturers named as SFEs by statute (CATL, BYD, Gotion, EVE Energy, Hithium, Envision/AESC) account for a substantial share of global battery cell production. FEOC-compliant BESS suppliers with U.S. manufacturing include Tesla (Gigafactory Nevada), LG Energy Solution (Holland, Michigan), Samsung SDI, and Panasonic. For larger commercial and utility-scale storage, supply remains constrained enough that multiple major banks have paused on tax equity financing pending clearer supply certainty.

Storage-specific FEOC rules: why the bar is higher

Battery energy storage systems face a structurally tighter compliance challenge than solar, for two reasons.

First, the MACR threshold starts at 55 percent for storage projects beginning construction in 2026, versus 40 percent for solar. That 15-percentage-point gap is consequential given that battery cells represent approximately 52 percent of total BESS equipment cost under the IRS safe harbor cost tables. If the cells in a storage system come from an SFE-named manufacturer, the project almost certainly fails the 55 percent non-PFE threshold immediately, regardless of the origin of everything else in the system.

Second, the storage supply chain is more layered. A BESS developer may source compliant battery modules while the cells inside those modules were manufactured by a PFE. Notice 2026-15 requires tracing at the manufactured product component level, which means the compliance analysis cannot stop at the module maker. It requires visibility into cell sourcing, which requires cooperation from the battery manufacturer beyond what most commercial transactions have historically involved.

The OBBBA's standalone storage exemption from the July 4, 2026, construction deadline does not change the FEOC rules. Standalone storage retains its ITC runway through 2033, which is favorable relative to solar. But a standalone storage project beginning construction in 2027 must meet the 60 percent non-PFE threshold for that year. The longer runway buys time to find compliant supply; it does not reduce the compliance obligation.

Any commercial solar-plus-storage project must run the FEOC analysis separately for the PV array and the battery system. A supply mix that clears the 40 percent solar threshold for 2026 will not automatically clear the 55 percent storage threshold. This is the calculation that most commercial owners learning about FEOC for the first time have not done yet.

Documentation requirements: what owners need from EPCs

Notice 2026-15 creates documentation obligations that flow up the supply chain to the project owner. Three layers.

Layer 1: Supplier certifications. Under the certification safe harbor, a project owner can rely on written certifications from each equipment supplier that the supplier is not a PFE. The Notice specifies required content: the supplier's name and jurisdiction of organization, an attestation that it does not meet the SFE or FIE definition, and a representation that it will notify the developer if status changes. A standard module purchase order does not satisfy this. A FEOC certificate is a legal attestation about the supplier's ownership structure, and it needs to match the format the Notice describes.

Layer 2: MACR calculation documentation. The developer or owner must calculate and document the MACR for each qualified facility, and retain the supporting backup. If using the cost percentage safe harbor from Notice 2025-08, the documentation must identify which manufactured products and components are present, apply the assigned percentages, determine which are PFE-sourced, and produce a documented cost ratio. This paperwork must exist before the credit is claimed, not assembled later during an audit.

Layer 3: Effective control review. Any contract with a Chinese manufacturer covering warranty, maintenance, monitoring, or technology licensing must be reviewed against the effective control standard. Since Treasury has not yet issued final guidance on that definition, legal review is not optional. A provision giving a manufacturer remote system access or the right to override dispatch decisions may be precisely the kind of arrangement that triggers FIE status.

For commercial owners negotiating an EPC agreement today, the right approach is to require a formal FEOC compliance package as a contract deliverable. That package should include: written PFE certifications from every module, inverter, and battery supplier; a documented MACR calculation for each facility; identification of the safe harbor method used; and a representation that no certification was known to be inaccurate at closing. The 10-year recapture window means this documentation protects you well past commissioning.

Recapture risk: the 10-year liability in business terms

The OBBBA's recapture provision is the one most commercial owners underestimate.

If a taxpayer claims a Section 48E ITC and then makes payments under a post-commissioning contract that gives a Specified Foreign Entity effective control over the project, the full claimed credit must be repaid, plus interest from the original tax year. This is not a going-forward disqualification. It triggers recapture of the entire credit, plus interest, plus potentially a 20 percent accuracy-related penalty if the IRS determines the credit was claimed without adequate documentation. The IRS can audit and initiate recapture proceedings up to six years after the credit is claimed. For a 2026 project claiming an ITC in its 2026 tax return, that audit window remains open until at least 2032. Combined with the 10-year recapture period, the liability tail for a 2026 project runs into the mid-2030s.

In concrete terms: a 500 kW commercial project with a $375,000 ITC carries a full $375,000 recapture exposure if, three years after commissioning, the owner signs an extended O&M contract with a manufacturer the IRS later determines was a FIE exercising effective control. Many commercial solar maintenance agreements give the EPC or module manufacturer remote access to monitoring systems, warranty-related system adjustments, or performance override capabilities. Whether those provisions constitute effective control is exactly the question Treasury has not yet answered.

The practical response: review every post-commissioning service contract before it is signed, and each time it is renewed. The compliance obligation does not end at interconnection. It runs through the life of every service agreement.

Colorado context: bonus credits and what FEOC changes

Colorado commercial solar projects have two bonus adders worth examining in the FEOC context.

Domestic content adder (10 percent): A project qualifies for an additional 10 percent ITC adder if it meets domestic content requirements: 100 percent U.S.-manufactured iron and steel for structural components, and at least 40 percent U.S.-manufactured content for other manufactured products. FEOC compliance and domestic content compliance use different component lists, different cost allocation methods, and different thresholds. A project can be FEOC-compliant and still miss the domestic content adder if the U.S.-manufactured modules contain PFE-sourced cells. Running both analyses separately is required.

Energy Community adder (10 percent): Projects in designated Energy Communities can stack another 10 percent adder. Several Colorado Front Range and Eastern Plains locations qualify under the census-tract economic significance or fossil fuel employment criteria. The Energy Community adder has no FEOC entanglement; a FEOC-compliant project in a qualifying Colorado location can stack the base 30 percent ITC, the 10 percent domestic content adder, and the 10 percent Energy Community adder for a potential 50 percent total credit.

For a 500 kW Colorado commercial project with a $1.25 million installed basis, the difference between the base 30 percent ITC and a fully stacked 50 percent ITC is $250,000. The compliance cost of FEOC documentation and legal review is well under that increment. The bigger risk is not spending that money and losing the credit.

What to do before signing a commercial solar contract now

Five steps reduce FEOC exposure before contract execution.

One: Require a written FEOC compliance plan from the developer as a contract deliverable. It should name every major manufactured product, identify the manufacturer, confirm PFE or non-PFE status, and show a preliminary MACR calculation. If a developer cannot produce this before signing, that is a diligence issue, not a paperwork issue.

Two: Require written PFE certifications from each equipment supplier as a contract deliverable with a deadline before commissioning. These are not standard product certifications; they are legal attestations about ownership structure.

Three: Run the FEOC analysis separately for the PV array and the battery system on any project that includes storage. The thresholds differ, the components differ, and a combined calculation will understate the storage compliance exposure.

Four: Have every post-commissioning service contract reviewed for effective control provisions before signing. This includes the O&M agreement, any performance guarantee, and any remote monitoring arrangement that gives a third party operational authority.

Five: Plan to revisit documentation when Treasury publishes the formal safe harbor tables required by December 31, 2026. The interim framework in Notice 2026-15 governs 2026 projects, but the final tables may require adjustments. A 60-day grace period applies for qualified facility and energy storage technology credits after the new tables are published; no grace period applies for Section 45X eligible components.

The FEOC rules do not make commercial solar uneconomic. A 2026 project with FEOC-compliant supply, complete documentation, and no effective-control exposure still carries a 30 percent base ITC, 100 percent bonus depreciation in year one, and the potential for stacked bonus adders. What the rules change is the administrative load the EPC contract now has to carry, and the 10-year liability exposure if that load is carried carelessly. For a project where documentation was assembled hastily, the exposure is the entire credit value. Not a portion of it.


Solara Pro is a commercial solar developer based in Broomfield, Colorado. FEOC guidance is evolving quickly. This briefing reflects Treasury and IRS guidance current as of August 2026. It is not tax or legal advice; owners should engage qualified counsel and verify all positions against current IRS notices before commitment.